Jeevan Dhara Expected Time Line

Time Line :-

Land Purchased – Oct 2012

Master Plan & Zoning Approved – Nov 2014

Tarneit Station Opened – 2015

Tarneit Central Shopping Centre Opened – Oct, 2017

Development Plans submitted to Council – Oct, 2017

Town Planning Approval expected by – Mid 2018

Notice for Deposit after Building Design Approvals – Mid 2018

70% on Deposit target achieved upon Contract sign/ Apartment by– Mid-Late 2018

Jeevan Dhara  Keys Handover – Mid-Late 2019